Building your own home in Spain: from plot to keys
Buying a plot and having your own house built is quite possible on the Costa Blanca — if you know what kind of land you are buying. This is the route.
I do not only help with buying an existing house, but also with building: from finding the plot to handover. It is a longer process with more parties involved, and the first step is the most important one. This is how it works.
Step 1: what kind of land?
Everything starts with the planning status of the plot, and in Spain that is no detail.
Building land (suelo urbano). Land in or on the edge of a village or urbanisation, with roads, water and electricity at the boundary. Here you may build within the rules of the local plan: maximum built area, height, distance to the boundary. This is the straight road.
Land for development (suelo urbanizable). Designated to become building land one day, but the infrastructure is not there yet and its cost falls on the owners. Nice on paper, often years of waiting.
Rural land (suelo rústico / no urbanizable). Most of the inland area. Building a house on rural land is heavily restricted in the Comunidad Valenciana: there are requirements on minimum plot size (often 10,000 m² or more) and on use, and in many areas it is simply not allowed. Buying an existing, legal house on rural land is fine; building a new one is another story.
Before you reserve a plot, your lawyer or architect requests a planning certificate from the town hall (cédula de garantía urbanística or certificado urbanístico). It states in black and white what may be built on this plot. A plot without that paper is not a plot but a question.
Step 2: buying the plot
The purchase process is the same as for a house — reservation, checks, arras, notary — with one extra check: is the plot where the registry says it is, are the boundaries correct, and are there easements (a path, a neighbour's water pipe). A surveyor (topógrafo) measures the plot; those few hundred euros prevent arguments about a strip of land that later turns out to be the garage.
On the purchase of a plot you pay transfer tax (ITP, 10% in the Comunidad Valenciana) if you buy from a private individual, or VAT (21%) if you buy from a company.
Step 3: the architect and the design
In Spain an architect (arquitecto) draws up the design, and that is compulsory. First a preliminary design (proyecto básico), used to apply for the permit, then the execution design (proyecto de ejecución) on which the builder prices the work. Alongside the architect comes a technical architect (arquitecto técnico or aparejador) who supervises the work on site.
For the fees of both together, count on roughly 8 to 12% of the building cost. Always ask for a fixed price in advance.
Step 4: the permit
The town hall issues the building permit (licencia de obra mayor) on the basis of the preliminary design. How long that takes varies by municipality: from a few months to a year is normal. With the permit you pay a municipal tax on the building cost (ICIO, a few percent) and fees.
Step 5: the build
Choose the builder on a comparable quote — the architect helps with that — and set out in the contract: the price, payment instalments tied to progress, the completion date and a penalty for delay. On the construction of a house you pay 10% VAT. A detached house of average size usually takes twelve to eighteen months.
A ten-year insurance (seguro decenal) against structural defects is compulsory if you want to sell the house within ten years; arrange it from the start, because it requires inspection during the build.
Step 6: handover and paperwork
After the build come the architect's completion certificate (certificado final de obra), the municipal declaration that the house may be occupied (licencia de primera ocupación or the declaration the municipality uses for it), the connection of water and electricity, and at the notary the new-build deed (declaración de obra nueva), which puts the house on the land registry. Only then is it officially a house.
What it costs, roughly
- the plot, plus 10% tax and transfer costs
- the build: depends on finish and terrain; the price per square metre varies a lot, ask for a current indication
- architect and technical architect: roughly 8–12% of the building cost
- permit and ICIO: a few percent of the building cost
- VAT on the build: 10%
- connections, insurance, notary and registry: a few thousand euros
My role
I find the plot, have the planning certificate requested before you sign anything, put you in touch with an architect and builders I know, and remain your point of contact during the build — even when you are not in Spain. Building from a distance is possible; it just needs someone on the spot who looks on your behalf.